Quote from email to me from MG UK on 14th June : -
In addition, for MG orders that were placed in January the estimated lead time would be 8 months, but subject to change, which could be even sooner once the production has commenced.
The last ship that arrived left Shanghai on 1st June and arrived today. That is 4 weeks including stops.
To work out minimum delivery time allow 2 weeks to manufacture / deliver to port and load on ship.
Then 2 weeks to unload / ship to dealer / PDI.
We are therefore looking at 2 months minimum delivery time.
They need to start manufacture next week to hit 8 month. To hit 9 month delivery they need to start manufacture next month.
Confidence level- currently very low.
Especially when Cars2 at Barnsley are advertising 2 in stock for immediate delivery and a number of other dealers claiming to have stock orders coming soon.
The larger dealers have a lot more clout when it comes to getting cars from MG UK. Unfortunately I chose a small dealer close to home and they have no voice with MG to get a single LR car - even on the orders placed in November last year. Rant over - let’s see what happens?